Grand River Edges Trail, Blue Bridge to JW Marriott

Timeline:
Construction Start: Summer 2024
Completion Goal: Spring 2025
Scope:
Improvements on east riverbank from the Blue Bridge to JW Marriott/Louis St. will include bank stabilization, new plantings and universal access along the River edge.
EST. Project Budget:
$1.7 million
Funding Sources:
Grand Rapids Downtown Development Authority, American Rescue Plan Act (City of GR)
Project Partners:
Lead: City of Grand Rapids
Design: VIRIDIS Design Group, Fishbeck
Contractor: Katerberg VerHage Inc.
Partners: Downtown Grand Rapids Inc.